Skip to main content

Surya Square, Wadala West

Lapsed

by Rajasthan Construction Pvt Ltd · Wadala West, Mumbai 400031 · Map

Launched
May 20232 yrs 7 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
15 of 2952% · 19 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale15 booked out of 29 units

Rehab19 units for existing members

Total 48 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
24
2 BHK
13
3 BHK
1
Other units
9
Total units
48
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
29
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%15
100%100%0%15
100%100%0%15
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Surya Square by Rajasthan Construction Pvt Ltd is a 48-unit BMC-sanctioned project in Wadala West, Mumbai 400031, launched in May 2023; its MahaRERA registration has lapsed. 15 units booked out of 29 units for sale. The concrete structure (RCC) is complete.

Read full summary

Surya Square is a BMC-sanctioned project by Rajasthan Construction Pvt Ltd in Wadala West, Mumbai 400031, registered with MahaRERA as P51900051054. It was launched in May 2023. It has 48 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 48 units, 29 are for sale and 19 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

15 units booked out of 29 units for sale (52%).