Jade Solitaire, Matunga
by National Happy Homes · Matunga, Mumbai 400019 · Map
- Launched
- Jun 20233 yrs 9 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 5 of 771% · 4 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 7 units
Rehab4 units for existing members
Land-owner share4 units, not for sale
Total 15 units. Rehab and land-owner units are not for sale.
Project facts
- 2 BHK
- 2
- 3 BHK
- 5
- 4 BHK
- 8
- Total units
- 15
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 7
- Rehab units
- 4
- Land-owner share (not for sale)
- 4
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 5 | |
| 100% | 100% | 0% | 5 | |
| 100% | 70% | 0% | 5 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400019
Projects with up to 30 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 2 yrs 9 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Mar 2027 | Jul 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 71% | 37% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Shayona, Matunga
- Jade Acharya, Matunga
- Shri Satya Sadan, Matunga
- Techno Kalpana, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shayona | June 2023 | December 2026 | 100% | 2 units booked out of 10 units for sale |
| Jade Acharya | September 2023 | December 2026 | 100% | 6 units booked out of 11 units for sale |
| Shri Satya Sadan | December 2023 | March 2026 | 100% | 1 unit booked out of total 17 units |
| Techno Kalpana | October 2022 | December 2025 | 100% | 17 units booked out of total 19 units |
About this project
Jade Solitaire by National Happy Homes is a 15-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in June 2023 with possession due in March 2027. 5 units booked out of 7 units for sale. The concrete structure (RCC) is complete.
Read full summary
Jade Solitaire is a BMC-sanctioned project by National Happy Homes in Matunga, Mumbai 400019, registered with MahaRERA as P51900051442. It was launched in June 2023. It has 15 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 15 units, 7 are for sale, 4 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.
5 units booked out of 7 units for sale (71%).