- Launched
- Sep 20233 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 6 of 1155% · 9 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 11 units
Rehab9 units for existing members
Land-owner share6 units, not for sale
Total 26 units. Rehab and land-owner units are not for sale.
Project facts
- 2 BHK
- 10
- 3 BHK
- 16
- Total units
- 26
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 9
- Land-owner share (not for sale)
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 6 | |
| 100% | 100% | 55% | 6 | |
| 100% | 95% | 0% | 6 | |
| 100% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400019
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 55% | 20% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Shayona, Matunga
- Shri Satya Sadan, Matunga
- Jade Solitaire, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shayona | June 2023 | December 2026 | 100% | 2 units booked out of 10 units for sale |
| Shri Satya Sadan | December 2023 | March 2026 | 100% | 1 unit booked out of total 17 units |
| Jade Solitaire | June 2023 | March 2027 | 100% | 5 units booked out of 7 units for sale |
About this project
Jade Acharya by Raghavendra Acharya & Others is a 26-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in September 2023 with possession due in December 2026. 6 units booked out of 11 units for sale. The concrete structure (RCC) is complete.
Read full summary
Jade Acharya is a BMC-sanctioned project by Raghavendra Acharya & Others in Matunga, Mumbai 400019, registered with MahaRERA as P51900052681. It was launched in September 2023. It has 26 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 11 are for sale, 9 are rehab units for existing members and 6 are the land-owner's share, not for sale.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
6 units booked out of 11 units for sale (55%).