Piramal Aranya - Ahan 2, Mazgaon

by Glider Buildcon Realtors Private Limited · Mazgaon, Mumbai 400010 · Map

Launched
Jun 20234 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked
174 of 29260% · 130 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
172
3 BHK
89
4 BHK
31
Total units
292
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 15%Dec 2025: Final finishes 15%Jul 2026: Final finishes 40%Oct 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%174
100%100%40%130
100%100%15%36
100%100%15%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Piramal Aranya - Ahan 2 by Glider Buildcon Realtors Private Limited (Piramal) is a 292-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in June 2023 with possession due in December 2027. 174 units booked out of total 292 units. The concrete structure (RCC) is complete.

Read full summary

Piramal Aranya - Ahan 2 is a BMC-sanctioned project by Glider Buildcon Realtors Private Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900051735. It was launched in June 2023. It has 292 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.

174 units booked out of total 292 units (60%). Since the July 2026 update, 44 more units have been booked.

Piramal's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA13
Total units across these projects3,823
Completed without extending the possession date5
Completed after an extension0
Lapsed3
Under construction5
Possession date extended on the builder's application0
Typical time from launch to 100% structure6 years 2 months
MahaRERA complaints (filed by or against the builder), all Piramal projects83 (11 of 13 projects)

See all Piramal projects →