Sea Face, Worli
by Lodha Developers Limited · Worli, Mumbai 400018 · Map
- Launched
- Nov 20235 yrs 3 mths promised
- Possession (MahaRERA)
- Feb 2029Not extended
- Concrete structure
- 13%Mid-construction
- Booked
- 9 of 2931% · 7 in Jul 2026
- Buildings
- 11.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 5+ BHK
- 29
- Total units
- 29
- Buildings
- 1
- Land
- 1.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 13% | 0% | 9 | |
| 100% | 9% | 0% | 7 | |
| 100% | 1% | 0% | 5 | |
| 20% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
Sea Face by Lodha Developers Limited is a 29-unit SRA-sanctioned project in Worli, Mumbai 400018, launched in November 2023 with possession due in February 2029. 9 units booked out of total 29 units. The concrete structure (RCC) is 13% complete.
Read full summary
Sea Face is an SRA-sanctioned project by Lodha Developers Limited in Worli, Mumbai 400018, registered with MahaRERA as P51900053592. It was launched in November 2023. It has 29 units in 1 building, with 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is February 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 13% complete, final finishes not started.
9 units booked out of total 29 units (31%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 9% to 13%.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.