Mariam Residency, Mandvi

Lapsed

by Al Hashmi Associates · Mandvi, Mumbai 400003 · Map

Launched
Jan 20243 mths originally promised
Possession (MahaRERA)
Apr 2026Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 270% · 21 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 27 units

Rehab21 units for existing members

Total 48 units. Rehab units are not for sale.

Project facts

1 RK
4
1 BHK
22
2 BHK
12
Other units
10
Total units
48
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
27
Rehab units
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%0
100%100%0%0
100%100%0%–
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mariam Residency by Al Hashmi Associates is a 48-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in January 2024; its MahaRERA registration has lapsed. 0 units booked out of 27 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mariam Residency is a BMC-sanctioned project by Al Hashmi Associates in Mandvi, Mumbai 400003, registered with MahaRERA as P51900054395. It was launched in January 2024. It has 48 units in 1 building: 38 homes (1 RK, 1 BHK and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 48 units, 27 are for sale and 21 are rehab units for existing members.

Possession was due in April 2026, after an extension of 2 years from the original April 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

0 units booked out of 27 units for sale (0%).