Satguru Serenity, Dadar West
by Utsav Developers · Dadar West, Mumbai 400028 · Map
- Launched
- May 20242 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 27
- 2 BHK
- 8
- 3 BHK
- 1
- Other units
- 34
- Total units
- 71
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400028
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 3 yrs |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2027 |
| Concrete structure (RCC) | 100% | 74% |
| Units booked | – | 72% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Shilp Serenity, Dadar West
- Shree Siddhi, Dadar West
- Buildarch Sakura, Dadar West
- Mansion 835, Dadar West
- Vision Crest, Dadar West
- SHIVAM - Embrace Azure Living, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shilp Serenity | May 2024 | December 2027 | 39% | 5 units booked out of 14 units for sale |
| Shree Siddhi | May 2024 | April 2027 | 100% | 6 units booked out of 8 units for sale |
| Buildarch Sakura | April 2024 | June 2027 | 95% | 14 units booked out of 20 units for sale |
| Mansion 835 | June 2024 | December 2027 | 34% | 1 unit booked out of 1 unit for sale |
| Vision Crest | July 2024 | December 2027 | 100% | 8 units booked out of 9 units for sale |
| SHIVAM - Embrace Azure Living | July 2024 | December 2027 | 52% | 0 units booked out of 7 units for sale |
About this project
Satguru Serenity by Utsav Developers is a 71-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in May 2024 with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
Satguru Serenity is a BMC-sanctioned project by Utsav Developers in Dadar West, Mumbai 400028, registered with MahaRERA as P51900055946. It was launched in May 2024. It has 71 units in 1 building: 37 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.