Mansion 835, Dadar West
by Rajadhiraj Construction LLP · Dadar West, Mumbai 400028 · Map
- Launched
- Jun 20243 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 34%Mid-construction
- Booked (free sale)
- 1 of 1100% · 21 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 1 unit
Rehab21 units for existing members
Total 22 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 2 BHK
- 19
- Other units
- 2
- Total units
- 22
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 1
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 34% | 0% | 1 | |
| 100% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400028
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 3 yrs |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Jul 2027 |
| Concrete structure (RCC) | 34% | 98% |
| Units booked (free sale) | 100% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- SHIVAM - Embrace Azure Living, Dadar West
- Shree Siddhi, Dadar West
- Sugee Samruddhi, Dadar West
- Shilp Serenity, Dadar West
- Satguru Serenity, Dadar West
- Buildarch Sakura, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| SHIVAM - Embrace Azure Living | July 2024 | December 2027 | 52% | 0 units booked out of 7 units for sale |
| Shree Siddhi | May 2024 | April 2027 | 100% | 6 units booked out of 8 units for sale |
| Sugee Samruddhi | May 2024 | August 2027 | 100% | 9 units booked out of total 10 units |
| Shilp Serenity | May 2024 | December 2027 | 39% | 5 units booked out of 14 units for sale |
| Satguru Serenity | May 2024 | December 2026 | 100% | – |
| Buildarch Sakura | April 2024 | June 2027 | 95% | 14 units booked out of 20 units for sale |
About this project
Mansion 835 by Rajadhiraj Construction LLP is a 22-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in June 2024 with possession due in December 2027. 1 unit booked out of 1 unit for sale. The concrete structure (RCC) is 34% complete.
Read full summary
Mansion 835 is a BMC-sanctioned project by Rajadhiraj Construction LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900076770. It was launched in June 2024. It has 22 units in 1 building: 20 homes (1 RK and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 1 is for sale and 21 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 34% complete, final finishes not started.
1 unit booked out of 1 unit for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 34%.