Royal Heights, Mahim

Ready to move

by S.A. Enterprises · Mahim, Mumbai 400016 · Map

Launched
Jun 20241 yr 6 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
9 of 3426% · 13 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 34 units

Rehab13 units for existing members

Total 47 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
32
2 BHK
10
Other units
4
Total units
47
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
13
Reserved units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 82%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%9
100%100%100%2
100%82%0%2
100%80%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400016

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 6 mths2 yrs 10 mths
Possession date extendedBy 1 yr0 of 3
Possession date (MahaRERA)Dec 2026Sep 2027
Concrete structure (RCC)100%85%
Units booked (free sale)26%57%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Royal Heights by S.A. Enterprises is a 47-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in June 2024 with possession due in December 2026. 9 units booked out of 34 units for sale. The concrete structure (RCC) is complete.

Read full summary

Royal Heights is a BMC-sanctioned project by S.A. Enterprises in Mahim, Mumbai 400016, registered with MahaRERA as P51900066542. It was launched in June 2024. It has 47 units in 1 building: 43 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 34 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

9 units booked out of 34 units for sale (26%). Since the July 2026 update, 7 more units have been booked.