Manikya, Mahim
by Aryaman Enterprises · Mahim, Mumbai 400016 · Map
- Launched
- Jul 20244 yrs 8 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 25 of 4457% · 20 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale25 booked out of 44 units
Rehab20 units for existing members
Total 64 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 28
- 2 BHK
- 33
- 3 BHK
- 1
- Other units
- 2
- Total units
- 64
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 44
- Rehab units
- 20
- Reserved units
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 5% | 25 | |
| 100% | 40% | 0% | 12 | |
| 100% | 0% | 0% | 7 | |
| 5% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400016
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 2 yrs 5 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Mar 2029 | Dec 2026 |
| Concrete structure (RCC) | 90% | 85% |
| Units booked (free sale) | 57% | 44% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Anj Ananda, Mahim
- Royal Heights, Mahim
- Residence 16, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anj Ananda | July 2024 | December 2026 | 85% | 8 units booked out of 18 units for sale |
| Royal Heights | June 2024 | December 2026 | 100% | 9 units booked out of 34 units for sale |
| Residence 16 | November 2024 | September 2027 | 85% | 29 units booked out of 30 units for sale |
About this project
Manikya by Aryaman Enterprises is a 64-unit SRA-sanctioned project in Mahim, Mumbai 400016, launched in July 2024 with possession due in March 2029. 25 units booked out of 44 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Manikya is an SRA-sanctioned project by Aryaman Enterprises in Mahim, Mumbai 400016, registered with MahaRERA as P51900077004. It was launched in July 2024. It has 64 units in 1 building: 62 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 44 are for sale and 20 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 5% complete.
25 units booked out of 44 units for sale (57%). Since the July 2026 update, 13 more units have been booked and the reported concrete structure (RCC) has gone from 40% to 90%.