Chhadva Iris, Dadar West

by Sheela Kheraj Chhadva · Dadar West, Mumbai 400028 · Map

Launched
Aug 20244 yrs 4 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 60% · 7 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 6 units

Rehab7 units for existing members

Land-owner share5 units, not for sale

Total 18 units. Rehab and land-owner units are not for sale.

Project facts

2 BHK
2
3 BHK
15
Other units
1
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
6
Rehab units
7
Land-owner share (not for sale)
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%0
100%100%0%0
100%100%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths3 yrs 3 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Dec 2027
Concrete structure (RCC)100%52%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Chhadva Iris by Sheela Kheraj Chhadva is an 18-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2024 with possession due in December 2028. 0 units booked out of 6 units for sale. The concrete structure (RCC) is complete.

Read full summary

Chhadva Iris is a BMC-sanctioned project by Sheela Kheraj Chhadva in Dadar West, Mumbai 400028, registered with MahaRERA as P51900077492. It was launched in August 2024. It has 18 units in 1 building: 17 homes (2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 6 are for sale, 7 are rehab units for existing members and 5 are the land-owner's share, not for sale.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

0 units booked out of 6 units for sale (0%).