Harsh Kusum Residence, Dadar West
Lapsed
by Tanishque Infrastructure · Dadar West, Mumbai 400028 · Map
- Launched
- Jan 20255 mths promised
- Possession (MahaRERA)
- Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 18
- 2 BHK
- 9
- Other units
- 1
- Total units
- 28
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 35% | – | |
| 100% | 80% | 35% | – | |
| 100% | 80% | 35% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400028
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Jun 2025 | Dec 2028 |
| Concrete structure (RCC) | 80% | 0% |
| Units booked | – | 17% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Sugee Gaurav, Dadar West
- Eirene Heights, Dadar West
- Saffron, Dadar West
- Chhadva Iris, Dadar West
- Suraj Aureva, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sugee Gaurav | December 2024 | March 2028 | 0% | – |
| Eirene Heights | November 2024 | December 2027 | 38% | 0 units booked out of 14 units for sale |
| Saffron | June 2025 | December 2028 | 0% | 6 units booked out of 18 units for sale |
| Chhadva Iris | August 2024 | December 2028 | 100% | 0 units booked out of 6 units for sale |
| Suraj Aureva | July 2025 | December 2031 | 0% | 19 units booked out of 26 units for sale |
About this project
Harsh Kusum Residence by Tanishque Infrastructure is a 28-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in January 2025; its MahaRERA registration has lapsed. The concrete structure (RCC) is 80% complete.
Read full summary
Harsh Kusum Residence is a BMC-sanctioned project by Tanishque Infrastructure in Dadar West, Mumbai 400028, registered with MahaRERA as P51900079015. It was launched in January 2025. It has 28 units in 1 building: 27 homes (1 RK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 35% complete.