Navkar Omnia, Mahalaxmi
by R V Property Ventures LLP · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Dec 20243 yrs promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 20 of 6630% · 87 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale20 booked out of 66 units
Rehab87 units for existing members
Total 153 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 122
- Other units
- 31
- Total units
- 153
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 66
- Rehab units
- 87
- Reserved units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 20 | |
| 100% | 100% | 0% | 16 | |
| 100% | 0% | 0% | 12 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 60–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 4 yrs 3 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2029 |
| Concrete structure (RCC) | 100% | 0% |
| Units booked (free sale) | 30% | 19% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- 7 Mahalaxmi - Tower 2, Mahalaxmi
- Al-Madina Chs, Mahalaxmi
- Icon By Merx, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 7 Mahalaxmi - Tower 2 | February 2025 | October 2031 | 0% | 49 units booked out of total 150 units |
| Al-Madina Chs | March 2025 | March 2029 | 0% | 13 units booked out of 118 units for sale |
| Icon By Merx | September 2025 | December 2029 | 0% | 25 units booked out of 135 units for sale |
About this project
Navkar Omnia by R V Property Ventures LLP is a 153-unit SRA-sanctioned project in Mahalaxmi, Mumbai 400011, launched in December 2024 with possession due in December 2027. 20 units booked out of 66 units for sale. The concrete structure (RCC) is complete.
Read full summary
Navkar Omnia is an SRA-sanctioned project by R V Property Ventures LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900078552. It was launched in December 2024. It has 153 units in 1 building: 122 homes (1 BHK) and 31 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 153 units, 66 are for sale and 87 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
20 units booked out of 66 units for sale (30%). Since the July 2026 update, 4 more units have been booked.