Icon By Merx, Mahalaxmi
by Magnum Land Realtors LLP · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Sep 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 25 of 13519% · 83 rehab units
- Buildings
- 21.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale25 booked out of 135 units
Rehab83 units for existing members
Total 218 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 50
- 2 BHK
- 94
- 3 BHK
- 50
- Other units
- 24
- Total units
- 218
- Buildings
- 2
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 135
- Rehab units
- 83
- Reserved units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 0% | 0% | 25 | |
| 0% | 0% | 0% | 17 | |
| 0% | 0% | 0% | 17 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400011
Projects with 90–400 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 4 yrs |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 19% | 30% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Al-Madina Chs, Mahalaxmi
- 7 Mahalaxmi - Tower 2, Mahalaxmi
- Navkar Omnia, Mahalaxmi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Al-Madina Chs | March 2025 | March 2029 | 0% | 13 units booked out of 118 units for sale |
| 7 Mahalaxmi - Tower 2 | February 2025 | October 2031 | 0% | 49 units booked out of total 150 units |
| Navkar Omnia | December 2024 | December 2027 | 100% | 20 units booked out of 66 units for sale |
About this project
Icon By Merx by Magnum Land Realtors LLP is a 218-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in September 2025 with possession due in December 2029. 25 units booked out of 135 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Icon By Merx is a BMC-sanctioned project by Magnum Land Realtors LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900080981. It was launched in September 2025. It has 218 units in 2 buildings: 194 homes (1, 2 and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 218 units, 135 are for sale and 83 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.
25 units booked out of 135 units for sale (19%). Since the July 2026 update, 8 more units have been booked.