Code 137, Mahim
by Prameya Developers · Mahim, Mumbai 400016 · Map
- Launched
- Mar 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 5 of 2223% · 26 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 22 units
Rehab26 units for existing members
Total 48 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 22
- 3 BHK
- 9
- Total units
- 48
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 22
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 5 | |
| 100% | 100% | 30% | 0 | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400016
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 4 yrs 6 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Jun 2029 | Dec 2029 |
| Concrete structure (RCC) | 100% | 50% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Avissa, Mahim
- Fortune Mastan, Mahim
- Residence 16, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avissa | June 2025 | December 2029 | 50% | 0 units booked out of 8 units for sale |
| Fortune Mastan | December 2024 | December 2030 | 0% | – |
| Residence 16 | November 2024 | September 2027 | 85% | 29 units booked out of 30 units for sale |
About this project
Code 137 by Prameya Developers is a 48-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in March 2025 with possession due in June 2029. 5 units booked out of 22 units for sale. The concrete structure (RCC) is complete.
Read full summary
Code 137 is a BMC-sanctioned project by Prameya Developers in Mahim, Mumbai 400016, registered with MahaRERA as P51900079421. It was launched in March 2025. It has 48 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 22 are for sale and 26 are rehab units for existing members.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.
5 units booked out of 22 units for sale (23%). Since the July 2026 update, 5 more units have been booked.