Avissa, Mahim
by Sealink Realtors · Mahim, Mumbai 400016 · Map
- Launched
- Jun 20254 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 0 of 80% · 27 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 8 units
Rehab27 units for existing members
Total 35 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 10
- 3 BHK
- 3
- 4 BHK
- 21
- Total units
- 35
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 27
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 8% | 0 | |
| 50% | 50% | 0% | 0 | |
| 50% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400016
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 3 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2029 |
| Concrete structure (RCC) | 50% | 25% |
| Units booked (free sale) | 0% | 18% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shree Nav Dadar, Mahim
- Pearl Elegance, Mahim
- Code 137, Mahim
- Shree Mahalakshmi Trinity, Mahim
- Ethics Oliver, Mahim
- Fortune Mastan, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Nav Dadar | June 2025 | December 2027 | 82% | 0 units booked out of 2 units for sale |
| Pearl Elegance | July 2025 | December 2028 | 50% | 4 units booked out of 18 units for sale |
| Code 137 | March 2025 | June 2029 | 100% | 5 units booked out of 22 units for sale |
| Shree Mahalakshmi Trinity | March 2025 | December 2027 | 0% | – |
| Ethics Oliver | October 2025 | December 2029 | 0% | 2 units booked out of 14 units for sale |
| Fortune Mastan | December 2024 | December 2030 | 0% | – |
About this project
Avissa by Sealink Realtors is a 35-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in June 2025 with possession due in December 2029. 0 units booked out of 8 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Avissa is a BMC-sanctioned project by Sealink Realtors in Mahim, Mumbai 400016, registered with MahaRERA as P51900080490. It was launched in June 2025. It has 35 units in 2 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 8 are for sale and 27 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 8% complete.
0 units booked out of 8 units for sale (0%).