Matunga Wing B, Sion

by Lodha Developers Limited · Sion, Mumbai 400022 · Map

Launched
Mar 20254 yrs promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
100%Nearing possession
Booked
34 of 5958%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
26
4 BHK
33
Total units
59
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 39%Jul 2026: Concrete structure (RCC) 76%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%34
100%76%0%34
100%39%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Matunga Wing B by Lodha Developers Limited is a 59-unit SRA-sanctioned project in Sion, Mumbai 400022, launched in March 2025 with possession due in March 2029. 34 units booked out of total 59 units. The concrete structure (RCC) is complete.

Read full summary

Matunga Wing B is an SRA-sanctioned project by Lodha Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as P51900079441. It was launched in March 2025. It has 59 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

34 units booked out of total 59 units (58%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 76% to 100%.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)