Skip to main content

41 Grandstand, Matunga

by Ramesh Builders · Matunga, Mumbai 400019 · Map

Launched
Mar 20254 yrs 3 mths promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
2 of 1315% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 13 units

Rehab12 units for existing members

Total 25 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
15
3 BHK
7
4 BHK
2
Total units
25
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 16%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 70%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 70%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%20%2
100%60%0%2
100%16%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400019

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths4 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2029Jun 2029
Concrete structure (RCC)70%18%
Units booked (free sale)15%41%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

41 Grandstand by Ramesh Builders is a 25-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in March 2025 with possession due in June 2029. 2 units booked out of 13 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

41 Grandstand is a BMC-sanctioned project by Ramesh Builders in Matunga, Mumbai 400019, registered with MahaRERA as P51900079615. It was launched in March 2025. It has 25 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 13 are for sale and 12 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 20% complete.

2 units booked out of 13 units for sale (15%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 70%.