41 Grandstand, Matunga
by Ramesh Builders · Matunga, Mumbai 400019 · Map
- Launched
- Mar 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 2 of 1315% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 13 units
Rehab12 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 15
- 3 BHK
- 7
- 4 BHK
- 2
- Total units
- 25
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 20% | 2 | |
| 100% | 60% | 0% | 2 | |
| 100% | 16% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400019
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 4 yrs 3 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2029 | Jun 2029 |
| Concrete structure (RCC) | 70% | 18% |
| Units booked (free sale) | 15% | 41% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Paramount, Matunga
- Amrut Villa, Matunga
- Chheda Imperial, Matunga
- Royal Oak, Matunga
- Hira House, Matunga
- Jade Wisteria, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paramount | March 2025 | February 2030 | 25% | 8 units booked out of 15 units for sale |
| Amrut Villa | February 2025 | October 2027 | 0% | 2 units booked out of 13 units for sale |
| Chheda Imperial | June 2025 | December 2029 | 10% | 2 units booked out of 7 units for sale |
| Royal Oak | June 2025 | November 2027 | 90% | 1 unit booked out of 5 units for sale |
| Hira House | December 2024 | December 2028 | 35% | 8 units booked out of 15 units for sale |
| Jade Wisteria | November 2024 | December 2029 | 0% | 11 units booked out of 15 units for sale |
About this project
41 Grandstand by Ramesh Builders is a 25-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in March 2025 with possession due in June 2029. 2 units booked out of 13 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
41 Grandstand is a BMC-sanctioned project by Ramesh Builders in Matunga, Mumbai 400019, registered with MahaRERA as P51900079615. It was launched in March 2025. It has 25 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 13 are for sale and 12 are rehab units for existing members.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 20% complete.
2 units booked out of 13 units for sale (15%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 70%.