Paramount, Matunga

by Gala Habitats LLP · Matunga, Mumbai 400019 · Map

Launched
Mar 20254 yrs 11 mths promised
Possession (MahaRERA)
Feb 2030Not extended
Concrete structure
25%Mid-construction
Booked (free sale)
8 of 1553% · 30 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 15 units

Rehab30 units for existing members

Total 45 units. Rehab units are not for sale.

Project facts

1 BHK
17
2 BHK
10
3 BHK
16
4 BHK
1
5+ BHK
1
Total units
45
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 20%Oct 2026: Concrete structure (RCC) 25%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%8
100%20%0%2
100%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400019

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Feb 2030Mar 2029
Concrete structure (RCC)25%22%
Units booked (free sale)53%24%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Paramount by Gala Habitats LLP is a 45-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in March 2025 with possession due in February 2030. 8 units booked out of 15 units for sale. The concrete structure (RCC) is 25% complete.

Read full summary

Paramount is a BMC-sanctioned project by Gala Habitats LLP in Matunga, Mumbai 400019, registered with MahaRERA as P51900079704. It was launched in March 2025. It has 45 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 45 units, 15 are for sale and 30 are rehab units for existing members.

Its registered possession date is February 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

8 units booked out of 15 units for sale (53%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 20% to 25%.