Yuu Luna, Chandivali
by Nahar Builders · Chandivali, Mumbai 400072 · Map
- Launched
- Sep 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 63%Mid-construction
- Booked
- 22 of 8526% · 10 in Jul 2026
- Buildings
- 20.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 85
- Total units
- 85
- Buildings
- 2
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 3% | 22 | |
| 100% | 18% | 0% | 10 | |
| 60% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
Yuu Luna by Nahar Builders is an 85-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in September 2025 with possession due in December 2029. 22 units booked out of total 85 units. The concrete structure (RCC) is 63% complete.
Read full summary
Yuu Luna is a BMC-sanctioned project by Nahar Builders in Chandivali, Mumbai 400072, registered with MahaRERA as PC1180002500839. It was launched in September 2025. It has 85 units in 2 buildings, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 63% complete, final finishes 3% complete.
22 units booked out of total 85 units (26%). Since the July 2026 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 18% to 63%.
Nahar's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 8 |
|---|---|
| Total units across these projects | 1,399 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Nahar projects | 0 (0 of 8 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.