Nahar projects in Mumbai

MahaRERA projects by Nahar registered 2017–2025 in Mumbai.

Projects registered with MahaRERA8
Total units across these projects1,399
Full record

MahaRERA projects registered 2017–2025 in Mumbai

Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction4
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Nahar projects0 (0 of 8 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Chandivali (7) · Mahalaxmi (1)

Under construction

ProjectVillageStagePossessionBooked
Nahar's Chandi Valley - Phase IChandivaliEarly stageDecember 2030101 units booked out of total 308 units
Winterberry Tower and PlazaChandivaliNearing possessionMarch 20272 units booked out of total 42 units
Yuu LunaChandivaliMid-constructionDecember 202922 units booked out of total 85 units
Yuu NovaChandivaliMid-constructionDecember 202840 units booked out of total 126 units
Completed
ProjectVillageStatus
AmaryllisChandivaliCompleted
Excalibur by NaharMahalaxmiCompleted
Nahar CayenneChandivaliCompleted
OliviaChandivaliCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us