Zen 16, Mahim

by Goodwill Infrastructure LLP · Mahim, Mumbai 400016 · Map

Launched
Jan 20262 yrs 11 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
10 of 2442% · 14 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 24 units

Rehab14 units for existing members

Total 38 units. Rehab units are not for sale.

Project facts

1 BHK
22
2 BHK
10
3 BHK
1
Other units
5
Total units
38
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
14
Reserved units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 15%Oct 2026: Excavation 80%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%0%0%10
15%0%0%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400016

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Mar 2029
Concrete structure (RCC)0%0%
Units booked (free sale)42%38%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Zen 16 by Goodwill Infrastructure LLP is a 38-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in January 2026 with possession due in December 2028. 10 units booked out of 24 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Zen 16 is a BMC-sanctioned project by Goodwill Infrastructure LLP in Mahim, Mumbai 400016, registered with MahaRERA as PM1170002502129. It was launched in January 2026. It has 38 units in 1 building: 33 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 24 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 80% complete, structure (RCC) not started, final finishes not started.

10 units booked out of 24 units for sale (42%). Since the July 2026 update, 1 more unit has been booked.