Ojas, Mahim
by Mauli Housing LLP · Mahim, Mumbai 400016 · Map
- Launched
- Mar 20263 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 4%Mid-construction
- Booked (free sale)
- 3 of 1718% · 24 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 17 units
Rehab24 units for existing members
Land-owner share7 units, not for sale
Total 48 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 21
- 2 BHK
- 25
- Other units
- 2
- Total units
- 48
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 17
- Rehab units
- 24
- Land-owner share (not for sale)
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 4% | 0% | 3 | |
| 100% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400016
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2029 | Jul 2029 |
| Concrete structure (RCC) | 4% | 0% |
| Units booked (free sale) | 18% | 18% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Harsh Oasis, Mahim
- Zen 16, Mahim
- Bawa Oceana, Mahim
- Avhad Beachfront Residences, Mahim
- Queen’s Corner, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Harsh Oasis | March 2026 | July 2029 | 0% | 5 units booked out of 28 units for sale |
| Zen 16 | January 2026 | December 2028 | 0% | 10 units booked out of 24 units for sale |
| Bawa Oceana | June 2026 | June 2031 | 0% | 0 units booked out of 27 units for sale |
| Avhad Beachfront Residences | June 2026 | December 2031 | 0% | 0 units booked out of total 60 units |
| Queen’s Corner | November 2025 | December 2028 | 0% | 15 units booked out of 22 units for sale |
About this project
Ojas by Mauli Housing LLP is a 48-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in March 2026 with possession due in December 2029. 3 units booked out of 17 units for sale. The concrete structure (RCC) is 4% complete.
Read full summary
Ojas is a BMC-sanctioned project by Mauli Housing LLP in Mahim, Mumbai 400016, registered with MahaRERA as PR1170002502773. It was launched in March 2026. It has 48 units in 1 building: 46 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 17 are for sale, 24 are rehab units for existing members and 7 are the land-owner's share, not for sale.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 4% complete, final finishes not started.
3 units booked out of 17 units for sale (18%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 4%.