Citadel, Matunga

by Tanmay Apartments Private Limited · Matunga, Mumbai 400019 · Map

Launched
Jun 20262 yrs promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
30%Mid-construction
Booked (free sale)
0 of 190% · 47 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 19 units

Rehab47 units for existing members

Total 66 units. Rehab units are not for sale.

Project facts

1 RK
24
1 BHK
3
2 BHK
9
3 BHK
1
4 BHK
2
Other units
27
Total units
66
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
19
Rehab units
47

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 30%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 30%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%0%0
100%30%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400019

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs5 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Jun 2028Jul 2031
Concrete structure (RCC)30%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Citadel by Tanmay Apartments Private Limited is a 66-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in June 2026 with possession due in June 2028. 0 units booked out of 19 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

Citadel is a BMC-sanctioned project by Tanmay Apartments Private Limited in Matunga, Mumbai 400019, registered with MahaRERA as PM1170002600660. It was launched in June 2026. It has 66 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 27 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 66 units, 19 are for sale and 47 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.

0 units booked out of 19 units for sale (0%).