Vishnu Meridian, Matunga
by Brown Bricks LLP · Matunga, Mumbai 400019 · Map
- Launched
- Oct 20267 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2033Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 138% · 9 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 13 units
Rehab9 units for existing members
Total 22 units. Rehab units are not for sale.
Project facts
- 1 RK
- 10
- 1 BHK
- 2
- 3 BHK
- 10
- Total units
- 22
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 9
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400019
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 2 mths | 4 yrs |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2033 | Jul 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 8% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Bellwether Cascade, Matunga
- Puje Ayana, Matunga
- Jade Regency, Matunga
- Citadel, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bellwether Cascade | August 2026 | December 2029 | 0% | 0 units booked out of 16 units for sale |
| Puje Ayana | June 2026 | March 2031 | 0% | 0 units booked out of 21 units for sale |
| Jade Regency | June 2026 | December 2031 | 0% | 0 units booked out of 10 units for sale |
| Citadel | June 2026 | June 2028 | 30% | 0 units booked out of 19 units for sale |
About this project
Vishnu Meridian by Brown Bricks LLP is a 22-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in October 2026 with possession due in December 2033. 1 unit booked out of 13 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Vishnu Meridian is a BMC-sanctioned project by Brown Bricks LLP in Matunga, Mumbai 400019, registered with MahaRERA as PR1170002602382. It was launched in October 2026. It has 22 units in 1 building, with 1 RK, 1 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 13 are for sale and 9 are rehab units for existing members.
Its registered possession date is December 2033, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
1 unit booked out of 13 units for sale (8%).