by Paradigm Friends Realtors LLP · Borivali West, Mumbai 400092 · Map

Launched
Jun 20253 yrs 7 mths promised
Possession (MahaRERA)
Jan 2029Not extended
Concrete structure
40%Mid-construction
Booked (free sale)
17 of 3057% · 34 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 30 units

Rehab34 units for existing members

Total 64 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
2
2 BHK
29
3 BHK
7
Other units
24
Total units
64
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
34

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 40%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%17
100%10%0%7
100%0%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths3 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jan 2029May 2028
Concrete structure (RCC)40%56%
Units booked (free sale)57%44%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shivalaya by Paradigm Friends Realtors LLP is a 64-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in June 2025 with possession due in January 2029. 17 units booked out of 30 units for sale. The concrete structure (RCC) is 40% complete.

Read full summary

Shivalaya is a BMC-sanctioned project by Paradigm Friends Realtors LLP in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002500137. It was launched in June 2025. It has 64 units in 1 building: 40 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 30 are for sale and 34 are rehab units for existing members.

Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.

17 units booked out of 30 units for sale (57%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 10% to 40%.

Paradigm's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA9
Total units across these projects5,095
Completed without extending the possession date0
Completed after an extension1
Lapsed0
Under construction8
Possession date extended on the builder's application2
MahaRERA complaints (filed by or against the builder), all Paradigm projects91 (5 of 9 projects)