Sanjay Abode – Shree Vijay C-D Wing CHSL, Borivali West

by Sanjay Habitats LLP · Borivali West, Mumbai 400092 · Map

Launched
Jul 20252 yrs 5 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
84%Mid-construction
Booked (free sale)
7 of 1258% · 24 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 12 units

Rehab24 units for existing members

Total 36 units. Rehab units are not for sale.

Project facts

2 BHK
24
3 BHK
12
Total units
36
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)84%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 73%Oct 2026: Concrete structure (RCC) 84%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 84%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%84%0%7
100%73%0%7
100%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Nov 2028
Concrete structure (RCC)84%38%
Units booked (free sale)58%38%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sanjay Abode – Shree Vijay C-D Wing CHSL by Sanjay Habitats LLP is a 36-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in July 2025 with possession due in December 2027. 7 units booked out of 12 units for sale. The concrete structure (RCC) is 84% complete.

Read full summary

Sanjay Abode – Shree Vijay C-D Wing CHSL is a BMC-sanctioned project by Sanjay Habitats LLP in Borivali West, Mumbai 400092, registered with MahaRERA as PR1180002500214. It was launched in July 2025. It has 36 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 12 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 84% complete, final finishes not started.

7 units booked out of 12 units for sale (58%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 73% to 84%.