Mandor Bliss, Vile Parle East

by Mandor Home Villa LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Jun 20253 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
22%Mid-construction
Booked (free sale)
4 of 2814% · 49 rehab units
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 28 units

Rehab49 units for existing members

Total 77 units. Rehab units are not for sale.

Project facts

1 RK
7
1 BHK
9
2 BHK
39
3 BHK
16
4 BHK
1
5+ BHK
1
Other units
4
Total units
77
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)22%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 65%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 22%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 22%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%22%0%4
90%0%0%3
65%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400057

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 2 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Dec 2028Sep 2027
Concrete structure (RCC)22%24%
Units booked (free sale)14%0%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Mandor Bliss by Mandor Home Villa LLP is a 77-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in June 2025 with possession due in December 2028. 4 units booked out of 28 units for sale. The concrete structure (RCC) is 22% complete.

Read full summary

Mandor Bliss is a BMC-sanctioned project by Mandor Home Villa LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as PM1180002500170. It was launched in June 2025. It has 77 units in 3 buildings: 73 homes (1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 77 units, 28 are for sale and 49 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 90% complete, structure (RCC) 22% complete, final finishes not started.

4 units booked out of 28 units for sale (14%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 22%.