Vijayraj Dhavalganga, Vile Parle East

by Vijayraj Developers LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20252 yrs 7 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
18 of 1995% · 33 rehab units
Buildings
30.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 19 units

Rehab33 units for existing members

Total 52 units. Rehab units are not for sale.

Project facts

1 RK
10
1 BHK
8
2 BHK
26
3 BHK
5
Other units
3
Total units
52
Buildings
3
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
19
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 90%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 90%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%90%0%18
100%70%0%18
0%0%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400057

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths2 yrs 9 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Mar 2028Jan 2028
Concrete structure (RCC)90%44%
Units booked (free sale)95%10%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vijayraj Dhavalganga by Vijayraj Developers LLP is a 52-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in August 2025 with possession due in March 2028. 18 units booked out of 19 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Vijayraj Dhavalganga is a BMC-sanctioned project by Vijayraj Developers LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as PR1180002500592. It was launched in August 2025. It has 52 units in 3 buildings: 49 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 52 units, 19 are for sale and 33 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation 90% complete, structure (RCC) 90% complete, final finishes not started.

18 units booked out of 19 units for sale (95%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 70% to 90%.