Skip to main content

Yuu Nova, Chandivali

by Nahar Builders · Chandivali, Mumbai 400072 · Map

Launched
Jul 20253 yrs 5 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
60%Mid-construction
Booked
40 of 12632% · 21 in Jul 2026
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
102
1 BHK
2
Other units
22
Total units
126
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%40
100%25%0%21
100%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Yuu Nova by Nahar Builders is a 126-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in July 2025 with possession due in December 2028. 40 units booked out of total 126 units. The concrete structure (RCC) is 60% complete.

Read full summary

Yuu Nova is a BMC-sanctioned project by Nahar Builders in Chandivali, Mumbai 400072, registered with MahaRERA as PM1180002500398. It was launched in July 2025. It has 126 units in 2 buildings: 104 homes (1 RK and 1 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

40 units booked out of total 126 units (32%). Since the July 2026 update, 19 more units have been booked and the reported concrete structure (RCC) has gone from 25% to 60%.

Nahar's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA8
Total units across these projects1,399
Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction4
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Nahar projects0 (0 of 8 projects)

See all Nahar projects →