Aum Aura, Santacruz West
by M/S Aum Serenity · Santacruz West, Mumbai 400054 · Map
- Launched
- Aug 20251 yr 11 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 40% · 13 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 4 units
Rehab13 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 5
- 3 BHK
- 9
- Other units
- 3
- Total units
- 17
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 4
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 90% | 0% | 0% | 0 | |
| 90% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400054
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 3 yrs |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Jul 2027 | Dec 2028 |
| Concrete structure (RCC) | 0% | 12% |
| Units booked (free sale) | 0% | 23% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Aatmay, Santacruz West
- Saras Avenue, Santacruz West
- Mukta, Santacruz West
- Armaan, Santacruz West
- Vaayu, Santacruz West
- Krishna Residency, Santacruz West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aatmay | July 2025 | December 2028 | 25% | 0 units booked out of 5 units for sale |
| Saras Avenue | July 2025 | June 2028 | 0% | 0 units booked out of 3 units for sale |
| Mukta | June 2025 | March 2029 | 60% | 3 units booked out of 3 units for sale |
| Armaan | November 2025 | December 2030 | 0% | 0 units booked out of 9 units for sale |
| Vaayu | November 2025 | December 2028 | 0% | 13 units booked out of 16 units for sale |
| Krishna Residency | November 2025 | December 2027 | 100% | 6 units booked out of total 13 units |
About this project
Aum Aura by M/S Aum Serenity is a 17-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2025 with possession due in July 2027. 0 units booked out of 4 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Aum Aura is a BMC-sanctioned project by M/S Aum Serenity in Santacruz West, Mumbai 400054, registered with MahaRERA as PM1180002500449. It was launched in August 2025. It has 17 units in 1 building: 14 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 4 are for sale and 13 are rehab units for existing members.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.
0 units booked out of 4 units for sale (0%).