Aatmay, Santacruz West
by Apv Developers · Santacruz West, Mumbai 400054 · Map
- Launched
- Jul 20252 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 1 yr
- Concrete structure
- 25%Mid-construction
- Booked (free sale)
- 0 of 50% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 5 units
Rehab8 units for existing members
Total 13 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 1
- 2 BHK
- 4
- 3 BHK
- 6
- 4 BHK
- 1
- Total units
- 13
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 5
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 10% | 0 | |
| 80% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400054
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 2 yrs 9 mths |
| Possession date extended | By 1 yr | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2027 |
| Concrete structure (RCC) | 25% | 30% |
| Units booked (free sale) | 0% | 23% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Saras Avenue, Santacruz West
- Aum Aura, Santacruz West
- Mukta, Santacruz West
- The Adhiraj, Santacruz West
- Krishna Residency, Santacruz West
- Garden Crest, Santacruz West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Saras Avenue | July 2025 | June 2028 | 0% | 0 units booked out of 3 units for sale |
| Aum Aura | August 2025 | July 2027 | 0% | 0 units booked out of 4 units for sale |
| Mukta | June 2025 | March 2029 | 60% | 3 units booked out of 3 units for sale |
| The Adhiraj | April 2025 | December 2027 | 100% | 5 units booked out of 9 units for sale |
| Krishna Residency | November 2025 | December 2027 | 100% | 6 units booked out of total 13 units |
| Garden Crest | February 2025 | December 2027 | 0% | 0 units booked out of 10 units for sale |
About this project
Aatmay by Apv Developers is a 13-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in July 2025 with possession due in December 2028. 0 units booked out of 5 units for sale. The concrete structure (RCC) is 25% complete.
Read full summary
Aatmay is a BMC-sanctioned project by Apv Developers in Santacruz West, Mumbai 400054, registered with MahaRERA as PR1180002500195. It was launched in July 2025. It has 13 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 5 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2028, extended by 1 year from the original December 2027. Construction: excavation complete, structure (RCC) 25% complete, final finishes 10% complete.
0 units booked out of 5 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 25%.