Empire Aashirwad, Dahisar
by Empire Realty · Dahisar, Mumbai 400068 · Map
- Launched
- Sep 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 5%Mid-construction
- Booked (free sale)
- 29 of 8136% · 42 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 81 units
Rehab42 units for existing members
Total 123 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 11
- 2 BHK
- 65
- Other units
- 47
- Total units
- 123
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 81
- Rehab units
- 42
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 5% | 0% | 29 | |
| 60% | 0% | 0% | 11 | |
| 0% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400068
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2029 | Dec 2028 |
| Concrete structure (RCC) | 5% | 46% |
| Units booked (free sale) | 36% | 17% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Vhs Sterling, Dahisar
- Mohini Akshay, Dahisar
- Nutan Dahisar, Dahisar
- Gayatri CHSL, Dahisar
- Skymont Siddhi, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vhs Sterling | September 2025 | August 2028 | 100% | 26 units booked out of 49 units for sale |
| Mohini Akshay | September 2025 | December 2029 | 0% | 2 units booked out of 23 units for sale |
| Nutan Dahisar | August 2025 | December 2028 | 46% | 8 units booked out of 46 units for sale |
| Gayatri CHSL | November 2025 | August 2028 | 75% | 1 unit booked out of 16 units for sale |
| Skymont Siddhi | March 2025 | December 2029 | 35% | 45 units booked out of 54 units for sale |
About this project
Empire Aashirwad by Empire Realty is a 123-unit MHADA-sanctioned project in Dahisar, Mumbai 400068, launched in September 2025 with possession due in December 2029. 29 units booked out of 81 units for sale. The concrete structure (RCC) is 5% complete.
Read full summary
Empire Aashirwad is a MHADA-sanctioned project by Empire Realty in Dahisar, Mumbai 400068, registered with MahaRERA as PM1180002500778. It was launched in September 2025. It has 123 units in 1 building: 76 homes (1 and 2 BHK) and 47 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 123 units, 81 are for sale and 42 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.
29 units booked out of 81 units for sale (36%). Since the July 2026 update, 18 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 5%.
Empire Realty's track record in Mumbai
MahaRERA projects registered 2022–2026 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 690 |
| Completed without extending the possession date | 6 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 6 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years |
| MahaRERA complaints (filed by or against the builder), all Empire Realty projects | 0 (0 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.