Gayatri CHSL, Dahisar
by Nvp Realty LLP · Dahisar, Mumbai 400068 · Map
- Launched
- Nov 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Aug 2028Not extended
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 1 of 166% · 28 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 16 units
Rehab28 units for existing members
Total 44 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 6
- 2 BHK
- 37
- 3 BHK
- 1
- Total units
- 44
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 1 | |
| 100% | 50% | 0% | 1 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400068
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Aug 2028 | Dec 2028 |
| Concrete structure (RCC) | 75% | 30% |
| Units booked (free sale) | 6% | 35% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rajhans Vandana, Dahisar
- Mohini Akshay, Dahisar
- Vhs Sterling, Dahisar
- Empire Aashirwad, Dahisar
- New Parvati Apartment, Dahisar
- Nutan Dahisar, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rajhans Vandana | November 2025 | December 2027 | 80% | 6 units booked out of 15 units for sale |
| Mohini Akshay | September 2025 | December 2029 | 0% | 2 units booked out of 23 units for sale |
| Vhs Sterling | September 2025 | August 2028 | 100% | 26 units booked out of 49 units for sale |
| Empire Aashirwad | September 2025 | December 2029 | 5% | 29 units booked out of 81 units for sale |
| New Parvati Apartment | February 2026 | December 2028 | 15% | 4 units booked out of 12 units for sale |
| Nutan Dahisar | August 2025 | December 2028 | 46% | 8 units booked out of 46 units for sale |
About this project
Gayatri CHSL by Nvp Realty LLP is a 44-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in November 2025 with possession due in August 2028. 1 unit booked out of 16 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Gayatri CHSL is a BMC-sanctioned project by Nvp Realty LLP in Dahisar, Mumbai 400068, registered with MahaRERA as PR1180002501496. It was launched in November 2025. It has 44 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 16 are for sale and 28 are rehab units for existing members.
Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
1 unit booked out of 16 units for sale (6%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 75%.