Silver Serenity, Vikhroli

by Silver Built Ventures LLP · Vikhroli, Mumbai 400083 · Map

Launched
Jan 20264 yrs 10 mths promised
Possession (MahaRERA)
Nov 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
17 of 11015% · 41 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 110 units

Rehab41 units for existing members

Total 151 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
129
Other units
14
Total units
151
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
110
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400083

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths3 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Nov 2030Oct 2028
Concrete structure (RCC)0%43%
Units booked (free sale)15%88%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Silver Serenity by Silver Built Ventures LLP is a 151-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in January 2026 with possession due in November 2030. 17 units booked out of 110 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Silver Serenity is a MHADA-sanctioned project by Silver Built Ventures LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as PM1180002502073. It was launched in January 2026. It has 151 units in 1 building: 137 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 151 units, 110 are for sale and 41 are rehab units for existing members.

Its registered possession date is November 2030, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

17 units booked out of 110 units for sale (15%).