Truearth VEDAA, Vikhroli
by Truearth Developers Pvt Ltd · Vikhroli, Mumbai 400083 · Map
- Launched
- Apr 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 65%Mid-construction
- Booked (free sale)
- 91 of 9893% · 32 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale91 booked out of 98 units
Rehab32 units for existing members
Total 130 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 88
- 2 BHK
- 42
- Total units
- 130
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 98
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 65% | 0% | 91 | |
| 100% | 35% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 60–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2028 |
| Concrete structure (RCC) | 65% | 42% |
| Units booked (free sale) | 93% | 62% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Adityaraj Tapovan, Vikhroli
- High Pavilion, Vikhroli
- Unique Fortune, Vikhroli
- Mansarovar Residency, Vikhroli
- Adityaraj Pavilion, Vikhroli
- Silver Serenity, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Adityaraj Tapovan | March 2025 | December 2028 | 54% | 87 units booked out of 119 units for sale |
| High Pavilion | March 2025 | August 2027 | 79% | – |
| Unique Fortune | June 2025 | October 2028 | 43% | 82 units booked out of 93 units for sale |
| Mansarovar Residency | February 2025 | December 2027 | 40% | 37 units booked out of 60 units for sale |
| Adityaraj Pavilion | August 2025 | December 2029 | 4% | 48 units booked out of 116 units for sale |
| Silver Serenity | January 2026 | November 2030 | 0% | 17 units booked out of 110 units for sale |
About this project
Truearth VEDAA by Truearth Developers Pvt Ltd is a 130-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2025 with possession due in December 2027. 91 units booked out of 98 units for sale. The concrete structure (RCC) is 65% complete.
Read full summary
Truearth VEDAA is a MHADA-sanctioned project by Truearth Developers Pvt Ltd in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800079921. It was launched in April 2025. It has 130 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 98 are for sale and 32 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 65% complete, final finishes not started.
91 units booked out of 98 units for sale (93%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 35% to 65%.