Skip to main content

Sayba Iris, Kurla East

by Star Rise · Kurla East, Mumbai 400024 · Map

Launched
Jan 20263 yrs promised
Possession (MahaRERA)
Jan 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
90 of 11181% · 40 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale90 booked out of 111 units

Rehab40 units for existing members

Total 151 units. Rehab units are not for sale.

Project facts

1 BHK
78
2 BHK
64
Other units
9
Total units
151
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
111
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%90
100%0%0%46

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400024

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 7 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jan 2029Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)81%30%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sayba Iris by Star Rise is a 151-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in January 2026 with possession due in January 2029. 90 units booked out of 111 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Sayba Iris is a MHADA-sanctioned project by Star Rise in Kurla East, Mumbai 400024, registered with MahaRERA as PM1180002502189. It was launched in January 2026. It has 151 units in 1 building: 142 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 151 units, 111 are for sale and 40 are rehab units for existing members.

Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

90 units booked out of 111 units for sale (81%). Since the July 2026 update, 44 more units have been booked.