by K D Constructions · Kurla East, Mumbai 400024 · Map

Launched
Sep 20252 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
20%Mid-construction
Booked (free sale)
80 of 11570% · 36 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale80 booked out of 115 units

Rehab36 units for existing members

Total 151 units. Rehab units are not for sale.

Project facts

1 BHK
64
2 BHK
76
Other units
11
Total units
151
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
115
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 20%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%80
100%5%0%0
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400024

Projects with 70–300 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs 4 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2027Jul 2029
Concrete structure (RCC)20%0%
Units booked (free sale)70%35%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Sayba Swarna by K D Constructions is a 151-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in September 2025 with possession due in December 2027. 80 units booked out of 115 units for sale. The concrete structure (RCC) is 20% complete.

Read full summary

Sayba Swarna is a MHADA-sanctioned project by K D Constructions in Kurla East, Mumbai 400024, registered with MahaRERA as PM1180002500790. It was launched in September 2025. It has 151 units in 1 building: 140 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 151 units, 115 are for sale and 36 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

80 units booked out of 115 units for sale (70%). Since the July 2026 update, 80 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 20%.