Urna 408A, Santacruz West

by Urna Evolved Living Private Limited · Santacruz West, Mumbai 400054 · Map

Launched
Feb 20263 yrs 10 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 30% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 3 units

Rehab13 units for existing members

Total 16 units. Rehab units are not for sale.

Project facts

2 BHK
2
3 BHK
10
4 BHK
1
5+ BHK
1
Other units
2
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
3
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Nov 2028
Concrete structure (RCC)0%0%
Units booked (free sale)0%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Urna 408A by Urna Evolved Living Private Limited is a 16-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in February 2026 with possession due in December 2029. 0 units booked out of 3 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Urna 408A is a BMC-sanctioned project by Urna Evolved Living Private Limited in Santacruz West, Mumbai 400054, registered with MahaRERA as PM1180002502277. It was launched in February 2026. It has 16 units in 1 building: 14 homes (2, 3, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 3 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 3 units for sale (0%).