Santacruz Aster Co-Op Housing Society Limited, Santacruz West

by Vira Platinum LLP · Santacruz West, Mumbai 400054 · Map

Launched
Jan 20262 yrs 2 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
6 of 2227% · 8 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 22 units

Rehab8 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

1 BHK
9
2 BHK
2
3 BHK
10
4 BHK
2
Other units
7
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
8
Reserved units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation5%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 5%Oct 2026: Excavation 5%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 5%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
5%0%0%6
5%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths3 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Mar 2029
Concrete structure (RCC)0%0%
Units booked (free sale)27%7%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Santacruz Aster Co-Op Housing Society Limited by Vira Platinum LLP is a 30-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in January 2026 with possession due in March 2028. 6 units booked out of 22 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Santacruz Aster Co-Op Housing Society Limited is an SRA-sanctioned project by Vira Platinum LLP in Santacruz West, Mumbai 400054, registered with MahaRERA as PR1180002502196. It was launched in January 2026. It has 30 units in 1 building: 23 homes (1, 2, 3 and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 22 are for sale and 8 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation 5% complete, structure (RCC) not started, final finishes not started.

6 units booked out of 22 units for sale (27%).