Elite Square, Kurla West

by I&A Realty Private Limited · Kurla West, Mumbai 400070 · Map

Launched
Mar 20263 yrs 3 mths promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 750% · 60 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 75 units

Rehab60 units for existing members

Total 135 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
111
3 BHK
1
Other units
15
Total units
135
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
75
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation40%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 80%Oct 2026: Excavation 40%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 40%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
40%0%0%0
80%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400070

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Jun 2029Oct 2029
Concrete structure (RCC)0%0%
Units booked (free sale)0%24%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Elite Square by I&A Realty Private Limited is a 135-unit MHADA-sanctioned project in Kurla West, Mumbai 400070, launched in March 2026 with possession due in June 2029. 0 units booked out of 75 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Elite Square is a MHADA-sanctioned project by I&A Realty Private Limited in Kurla West, Mumbai 400070, registered with MahaRERA as PM1180002502594. It was launched in March 2026. It has 135 units in 2 buildings: 120 homes (1, 2 and 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 135 units, 75 are for sale and 60 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation 40% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 75 units for sale (0%).