Deraiya Luxurio, Kurla West

by Deraiya Infra · Kurla West, Mumbai 400070 · Map

Launched
Feb 20263 yrs 4 mths promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
10 of 4721% · 36 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 47 units

Rehab36 units for existing members

Land-owner share5 units, not for sale

Total 88 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
26
2 BHK
35
3 BHK
17
Other units
10
Total units
88
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
36
Land-owner share (not for sale)
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%10
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400070

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 8 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jun 2029Jul 2029
Concrete structure (RCC)0%0%
Units booked (free sale)21%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Deraiya Luxurio by Deraiya Infra is an 88-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in February 2026 with possession due in June 2029. 10 units booked out of 47 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Deraiya Luxurio is a BMC-sanctioned project by Deraiya Infra in Kurla West, Mumbai 400070, registered with MahaRERA as PM1180002502524. It was launched in February 2026. It has 88 units in 1 building: 78 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 47 are for sale, 36 are rehab units for existing members and 5 are the land-owner's share, not for sale.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

10 units booked out of 47 units for sale (21%). Since the July 2026 update, 10 more units have been booked.