Shiv Jaya, Borivali East

by Navkarmik Infra & Development Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Mar 20265 yrs promised
Possession (MahaRERA)
Jul 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
82 of 12068% · 47 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale82 booked out of 120 units

Rehab47 units for existing members

Total 167 units. Rehab units are not for sale.

Project facts

1 RK
83
2 BHK
64
Other units
20
Total units
167
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
120
Rehab units
47
Reserved units
82

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%82
0%0%0%82

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 70–300 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs3 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jul 2029Jun 2030
Concrete structure (RCC)0%0%
Units booked (free sale)68%0%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shiv Jaya by Navkarmik Infra & Development Private Limited is a 167-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in March 2026 with possession due in July 2029. 82 units booked out of 120 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Shiv Jaya is an SRA-sanctioned project by Navkarmik Infra & Development Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as PM1180002503042. It was launched in March 2026. It has 167 units in 1 building: 147 homes (1 RK and 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 167 units, 120 are for sale and 47 are rehab units for existing members.

Its registered possession date is July 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

82 units booked out of 120 units for sale (68%).