Parle Kalpataru Chs Ltd, Vile Parle East
by Vijayraj Developers LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- Mar 20262 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 128% · 24 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 12 units
Rehab24 units for existing members
Total 36 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 28
- 3 BHK
- 7
- Other units
- 1
- Total units
- 36
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 0% | 0% | 1 | |
| 50% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 2 yrs 5 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Jul 2028 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 8% | 8% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- New Manibhuvan, Vile Parle East
- Arham Heritage, Vile Parle East
- Poddar Vasundhara, Vile Parle East
- Redevelopment Of Amarhind Chsl, Vile Parle East
- Shree Sadhana Co-Operative Housing Society Limited, Vile Parle East
- Accurate Neelkamal, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| New Manibhuvan | March 2026 | December 2026 | 70% | 1 unit booked out of 14 units for sale |
| Arham Heritage | April 2026 | January 2029 | 0% | 0 units booked out of 20 units for sale |
| Poddar Vasundhara | February 2026 | December 2027 | 42% | 1 unit booked out of 12 units for sale |
| Redevelopment Of Amarhind Chsl | April 2026 | September 2029 | 0% | 11 units booked out of 24 units for sale |
| Shree Sadhana Co-Operative Housing Society Limited | April 2026 | December 2029 | 0% | 0 units booked out of 14 units for sale |
| Accurate Neelkamal | January 2026 | February 2028 | 0% | 4 units booked out of 16 units for sale |
About this project
Parle Kalpataru Chs Ltd by Vijayraj Developers LLP is a 36-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in March 2026 with possession due in December 2028. 1 unit booked out of 12 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Parle Kalpataru Chs Ltd is a BMC-sanctioned project by Vijayraj Developers LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as PM1180002503070. It was launched in March 2026. It has 36 units in 2 buildings: 35 homes (2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 12 are for sale and 24 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 95% complete, structure (RCC) not started, final finishes not started.
1 unit booked out of 12 units for sale (8%). Since the July 2026 update, 1 more unit has been booked.