New Manibhuvan, Vile Parle East

by Amul Enterprises · Vile Parle East, Mumbai 400057 · Map

Launched
Mar 20269 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
1 of 147% · 18 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 14 units

Rehab18 units for existing members

Total 32 units. Rehab units are not for sale.

Project facts

1 BHK
11
2 BHK
9
3 BHK
8
Other units
4
Total units
32
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 70%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%10%1
100%70%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)9 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2026Feb 2029
Concrete structure (RCC)70%0%
Units booked (free sale)7%4%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

New Manibhuvan by Amul Enterprises is a 32-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in March 2026 with possession due in December 2026. 1 unit booked out of 14 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

New Manibhuvan is an SRA-sanctioned project by Amul Enterprises in Vile Parle East, Mumbai 400057, registered with MahaRERA as PM1180002502660. It was launched in March 2026. It has 32 units in 2 buildings: 28 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 14 are for sale and 18 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 10% complete.

1 unit booked out of 14 units for sale (7%). Since the July 2026 update, 1 more unit has been booked.