Amulya Heights, Goregaon West

by Amulya Co Op Hsg Soc Ltd · Goregaon West, Mumbai 400104 · Map

Launched
Apr 20264 yrs 8 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
18 of 6926% · 36 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 69 units

Rehab36 units for existing members

Total 105 units. Rehab units are not for sale.

Project facts

2 BHK
77
3 BHK
15
Other units
13
Total units
105
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
69
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%18
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400104

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths3 yrs 3 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2030Jul 2029
Concrete structure (RCC)0%0%
Units booked (free sale)26%11%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Amulya Heights by Amulya Co Op Hsg Soc Ltd is a 105-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in April 2026 with possession due in December 2030. 18 units booked out of 69 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Amulya Heights is a MHADA-sanctioned project by Amulya Co Op Hsg Soc Ltd in Goregaon West, Mumbai 400104, registered with MahaRERA as PM1180002600014. It was launched in April 2026. It has 105 units in 1 building: 92 homes (2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 105 units, 69 are for sale and 36 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

18 units booked out of 69 units for sale (26%).