Skip to main content

Vivere, Goregaon West

by Kolte-Patil Developers Limited · Goregaon West, Mumbai 400104 · Map

Launched
Mar 20264 yrs 5 mths promised
Possession (MahaRERA)
Aug 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
19 of 9021% · 146 rehab units
Buildings
21.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale19 booked out of 90 units

Rehab146 units for existing members

Total 236 units. Rehab units are not for sale.

Project facts

2 BHK
155
3 BHK
42
Other units
39
Total units
236
Buildings
2
Land
1.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
90
Rehab units
146

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation24%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 24%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 24%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
24%0%0%19
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400104

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths4 yrs 2 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Aug 2030Feb 2031
Concrete structure (RCC)0%0%
Units booked (free sale)21%27%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vivere by Kolte-Patil Developers Limited is a 236-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in March 2026 with possession due in August 2030. 19 units booked out of 90 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Vivere is a BMC-sanctioned project by Kolte-Patil Developers Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as PR1180002502702. It was launched in March 2026. It has 236 units in 2 buildings: 197 homes (2 and 3 BHK) and 39 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 236 units, 90 are for sale and 146 are rehab units for existing members.

Its registered possession date is August 2030, unchanged since launch. Construction: excavation 24% complete, structure (RCC) not started, final finishes not started.

19 units booked out of 90 units for sale (21%). Since the July 2026 update, 19 more units have been booked.