Adityaraj Bliss, Vikhroli
by Adityaraj Landscapes LLP · Vikhroli, Mumbai 400083 · Map
- Launched
- Apr 20263 yrs 10 mths promised
- Possession (MahaRERA)
- Feb 2030Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 30.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
Adityaraj Bliss by Adityaraj Landscapes LLP is a MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2026 with possession due in February 2030. Work on the concrete structure (RCC) has not started.
Read full summary
Adityaraj Bliss is a MHADA-sanctioned project by Adityaraj Landscapes LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as PM1180002600242. It was launched in April 2026. Its MahaRERA status is Active.
Its registered possession date is February 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.