Adityaraj projects in Mumbai
MahaRERA projects by Adityaraj registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 7 |
|---|---|
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Vikhroli (19) · Ghatkopar East (4) · Chembur (4) · Sion (2)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Adityaraj Bliss | Vikhroli | Early stage | February 2030 | – |
| Adityaraj Empire | Vikhroli | Early stage | December 2030 | – |
| Adityaraj Majestic | Chembur | Mid-construction | December 2027 | 124 units booked out of total 176 units |
| Adityaraj Park | Chembur | Mid-construction | December 2028 | – |
| Adityaraj Pavilion | Vikhroli | Mid-construction | December 2029 | 48 units booked out of 116 units for sale |
| Adityaraj Platinum | Chembur | Mid-construction | August 2028 | 54 units booked out of 94 units for sale |
| Adityaraj Springs | Chembur | Mid-construction | December 2028 | 60 units booked out of 128 units for sale |
| Adityaraj Tapovan | Vikhroli | Mid-construction | December 2028 | 87 units booked out of 119 units for sale |
| Sagar Sangeet Chs Adityaraj Paradise | Vikhroli | Nearing possession | December 2026 | 65 units booked out of total 130 units |
| Shraddha Chs Adityaraj Anchor | Vikhroli | Nearing possession | March 2027 | 115 units booked out of total 115 units |
Completed
| Project | Village | Status |
|---|---|---|
| Adityaraj Avenue | Vikhroli | Completed |
| Adityaraj Saphalya | Ghatkopar East | Completed |
| Gurukripa Chs | Vikhroli | Completed |
| Manoranjan Chs | Vikhroli | Completed |
| Navrang Chs Ltd | Sion | Completed |
| Sai Prasad | Vikhroli | Completed |
| Saptarshi Chs | Sion | Completed |
| Shivraj Chs Adityaraj Shivraj | Vikhroli | Completed |
| Suyog Chs | Vikhroli | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Adishakti Chs Adityaraj Prime | Vikhroli | Lapsed |
| Adityaraj Breeze | Vikhroli | Lapsed |
| Adityaraj Royale | Vikhroli | Lapsed |
| Adityaraj Shanti Sadan | Vikhroli | Lapsed |
| Adityaraj Signature | Vikhroli | Lapsed |
| Adityaraj Square | Vikhroli | Lapsed |
| Pragati Chs Adityaraj Central | Ghatkopar East | Lapsed |
| Shivneri Chs Adityaraj Gateway | Ghatkopar East | Lapsed |
| Suswagatam Chs Adityaraj Landmark | Vikhroli | Lapsed |
| Suvarnatula Chs Sai Adityaraj | Ghatkopar East | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.