Arkade Ascend, Malad West
by Arkade Developers Limited · Malad West, Mumbai 400064 · Map
- Launched
- Jul 20264 yrs 11 mths originally promised
- Possession (MahaRERA)
- Oct 2031Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 1 of 1651% · 196 rehab units
- Buildings
- 21.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 165 units
Rehab196 units for existing members
Total 361 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 33
- 2 BHK
- 237
- 3 BHK
- 79
- Other units
- 12
- Total units
- 361
- Buildings
- 2
- Land
- 1.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 165
- Rehab units
- 196
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 20% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
About this project
Arkade Ascend by Arkade Developers Limited is a 361-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in July 2026 with possession due in October 2031. 1 unit booked out of 165 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Arkade Ascend is a BMC-sanctioned project by Arkade Developers Limited in Malad West, Mumbai 400064, registered with MahaRERA as PM1180002601025. It was launched in July 2026. It has 361 units in 2 buildings: 349 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 361 units, 165 are for sale and 196 are rehab units for existing members.
Its registered possession date is October 2031, extended by 4 months from the original June 2031. Construction: excavation 20% complete, structure (RCC) not started, final finishes not started.
1 unit booked out of 165 units for sale (1%).
Arkade's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 27 |
|---|---|
| Total units across these projects | 3,356 |
| Completed without extending the possession date | 14 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 3 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Arkade projects | 15 (6 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.